HYDERABAD: Racing against time, officials of Pattiseema lift irrigation project have commissioned four pumping systems out of the total 24, ahead of the schedule. Enthused with the brisk pace of work, the project schedule has been advanced by 15 days. As per the earlier schedule, the project is to be completed by March 31, 2016. The project developer Megha...
↧